贵阳变压器的运行维护和检查

发布者:贵阳变压器厂    发布时间:2018-07-24
贵阳变压器的运行维护和检查
    1.监视运行和记录
    安装在变室盘上的电流表、电压表、功率表等,必须经常予以严格的监视。当有电阻式遥测温度的装置时,还应定期遥测贵阳变压器的上层油温,并作好运行记录,即定期抄表。
    每班至少记录抄表两次。发现三相负载不平衡,应及时调整接线,重新分配。但一般农村贵阳变压器以检查来代替监视。
 
    2.检查
    (1)检查时间,对于经常有值班人员的变所,对贵阳变压器每天应至少检查一次,每周夜晚检查一次。对于无人值班贵阳变压器,容量在3150kVA及以上,每10天至少检查一次,3150kVA以下每月至少检查一次。无值班人员的室每月至少检查一次,户外贵阳变压器每季至少检查一次。有严重缺陷、经常发生过负载和环境恶劣及气候突变情况下。以及新设备或经过检修改造的贵阳变压器在投运的72h内,应增加检查次数。高峰负载和雷雨季节可缩短至1-2月检查一次。对接有大量用户的贵阳变压器,运行人员应掌握其使用及负载变动情况,并控制其新增容量。定期测量负载,农忙农闲交接期间,适当安排测量.防止长期过负载。
 
Operation and maintenance and inspection of the transformer
 
    A surveillance operation and records
    The variable power distribution room on the distribution panel ammeter, voltmeter, power meter, must be kept under strict surveillance. Resistance telemetry temperature device should be regularly telemetry transformer top oil temperature, and well run record, namely, regular meter reading.
    Each class at least record the meter reading twice. Three-phase load imbalance, should promptly adjust the wiring, re-allocation. But generally rural transformer to replace the monitor to check.
 
    2 Check
    (1) Check the time, often the variable distribution of the staff on duty, every day of the transformer should be checked at least once a week night check. Unattended substation capacity of 3150kVA and above, every 10 days checked at least once, 3150kVA the following checked at least once a month. Power distribution room, no staff on duty at least once a month, outdoor distribution transformers on a quarterly basis at least once. Seriously flawed, often occurred under the load and a poor environment and climate mutation. As well as new equipment, modified or repaired transformer in operation within 72h should increase the number of checks. Peak load and storm season can be shortened to 1-2 month check. Docking a large number of users of the transformer, and operating personnel should master the use and load movements, and control of its new capacity. Periodic measurement of load, busy during the off-season transfer of appropriate arrangements for measurement. Prevent long-term overload.

快速通道

手机:

+131-8108-9999

座机:

+0635-8783-999

传真:

+0635-6066-688

邮箱:

858033047@qq.com

版权所有 ©  贵阳变压器,贵阳变压器厂,贵阳中能变压器厂
电话:0635-6066688  8783999 传真:0635-6066688  手机:13181089999  联系人:陈经理
邮箱:858033047@qq.com  QQ:858033047  鲁ICP备18003380号-2
技术支持:互联纵横

中能变压器二维码微信客服